2024 Project Updates:
Hanover Highlands Watermain Replacement Project Update: This week the contractor continued transferring services and began spot curb and gutter and sidewalk repair. This work will continue next week. While a service is being transferred, the resident will experience a short interruption in water service. Residents will be notified prior to their water service being interrupted.
IDOT Project at Lake Street and Gary Avenue: IDOT’s contractor began paving operations October 10th at Lake Street and Gary Avenue. This work will continue next week. Motorists should expect daily lane closures and significant delays. The use of alternate routes is advised.
Should you have any questions about either project, contact Engineering at 630-823-5700. Visit www.hpil.org/1117/construction-projects to see a map of the project areas.