Construction Updates Construction season is officially here! Check back here weekly for status updates. Arlington Drive Bridge Replacement Update: Crews installed a new watermain on Arlington Drive from Catalina to the bridge in preparation for the bridge replacement. Next week, the watermain will be tested and chlorinated. Schick Road Resurfacing Update: Crews began saw cutting and replacing areas of curb and gutter and sidewalk. This work will continue next week. 2025 Resurfacing Project Update: Crews began saw cutting and replacing areas of curb and gutter and sidewalk. This work will continue next week. Some driveways will be impacted, including the east side of Yorkshire Court, Asbury Court North, Sherwood Court North, Ramsgate Court North, Huntington Court North, Strathmore Lane, and the north side of Yorkshire Drive. If you have any project questions, contact Engineering at 630-823-5700 or visit www.hpil.org/1234/current-projects.
|