Pavement Preventative Maintenance

Project Location: Various Streets
Project Status: Complete
Bid Opening Date: January 28, 2025
Mandatory Pre Bid Meeting: No 
Construction Start Date:  April 28, 2025 
Construction Completion Date: May, 2025 
Contractor: Corrective Asphalt Materials, LLC
Construction Engineer: In House
Design Engineer: In House 
Awarded Construction Amount: $130,000
Adjusted Final Construction Amount: $120,145.60
Funding Source(s): Local 

Objective: To slow the natural deterioration of the Village's new asphalt streets. 

Description:  A rejuvenating agent is applied to the surface of newly paved asphalt streets, and then sand is placed on top of it to prevent tracking of the material. 

5/9/25 Update -  After a few rain delays, the contractor completed our annual pavement preventative maintenance project this week.  A rejuvenating agent was applied to the pavement surface to help extend the life of the pavement.